Concrete pour re-scheduled for Friday
The Wacker Drive deck pour at Washington, canceled last week, is rescheduled for Friday, June 3 at 1:30 a.m. It is expected to take place into the afternoon. The pour area is the largest yet and will require 200 trucks to deliver concrete to the construction site for about 10 hours. Trucks will access the site from Franklin. Access to all buildings will be maintained throughout the pour. Thanks for your continued patience.
Deck pour begins Wednesday
The next Wacker Drive deck pour will take place at the intersection of Wacker and Washington this Wednesday, May 25 at 1 a.m. The pour will last into the afternoon. As part of the pour, 200 trucks will deliver 1,800 cubic yards of concrete. Please plan your travel accordingly.