Project Schedule

Randolph St.

Start Date: January 2011
Completed: July 2011
Project:
Viaduct reconstruction starting at Randolph and heading south

Washington St.

Start Date: January 2011
Completed: July 2011
Project: Removal of ramp located at the intersection of Wacker and Washington. The ramp will be replaced with a landscaped median.

Madison St.

Start date: July 2011
Completed: December 2011
Project: Viaduct reconstruction starting at Madison and heading south

Monroe St.

Start Date: January 2012
Completed: June 2012
Project: Removal of ramp located at the intersection of Wacker and Monroe. The ramp will be replaced with a new one-way ramp to Lower Wacker.

Adams St.

Start Date: January 2012
Expected Completion: July 2012
Project: Removal of ramp located at the intersection of Wacker and Adams. The ramp will be replaced with a landscaped median.

Jackson St.

Start Date: June 2012
Expected Completion: November 2012
Project: Removal of ramp located at the intersection of Wacker and Jackson. The ramp will be replaced with a landscaped median.

Lower Wacker

Start Date: April 1, 2010
Expected Completion: November 2012
Project: Lower Wacker will undergo utility work between April 1 and Dec. 31, 2010, and reconstruction work from Jan. 1, 2011 through Nov. 30, 2012.

Congress Parkway Interchange

Start Date: Spring 2010
Expected Completion: November 2012
Access to/from Congress will continue to be closed to traffic from Wacker