Madison to Monroe
Crews will be pouring Latex for the deck between Madison and Monroe tomorrow morning. As part of the pour, the temporary pedestrian crossing north of Monroe will be removed today at 7 p.m.
Pedestrians can cross at Madison and use the Wacker sidewalks south of Madison. Once the pour is completed, the deck will need to cure and pedestrian access will be restricted on Wacker between Madison and Monroe. East-West travel on Madison will be permitted, but no pedestrians will be allowed to travel south on Wacker on either of the sidewalks between Madison and Monroe.
This new alignment will be in effect tomorrow at 7 p.m. until Tuesday morning.
Adams to Jackson
Deck forming also continues further south in the project.
The temporary sidewalk between Adams and Jackson will be removed Friday at 7 p.m. Crews will remove the sidewalk through the night and begin forming the deck over the weekend. The pedestrian path will be restored Monday morning.
Pedestrian Access Changes from Madison to Jackson
This entry was posted in Pedestrians and tagged adams, construction, jackson, monroe, pedestrians, randolph, reconstruction, revive wacker drive, Wacker Drive. Bookmark the permalink.